- 11 years of Enea brand on the Polish power market
- PLN 20 bn capital expenditures in 2014-2020
- PLN 4,5 bn for investments in green energy until 2020
- 1,9 GW additional generating capacity until 2020
Generation
- 3.3 GW installed electrical capacity
- 199 MW capacity installed in renewable energy sources
- 925 MWt installed heating capacity
- 9% of energy generated in Poland comes from our plants
The most modern power unit in Poland and in Europe
- 1.075 MW gross capacity
- 250 thou. hours of the planned working time
- 40 years a minimum by which the period of Kozienice Power Plant's operation will be prolonged
- in 2018 energy from Kozienice Power Plant will reach every 9th Polish citizen
Distribution
- 132 thou. km of power lines with connections
- 36 thou. switich stations
- 20% coverage of Poland
Trade
- 2.5 mln Customers
- 13% of electricity sold to end users in Poland